DETERMINATION OF THE DURATION OF THE INSTALLATION AND DISMANTLING OF FORMWORK BY INTEGER VALUATION

  • Г. М. Тонкачеєв
  • В. Г. Тонкачеєв

Abstract

The material in this article is based on a theoretical analysis and the experience of rationing the processes of erecting buildings and structures. Particular attention is paid to the problem of the choice of formwork systems for optimizing the processes of building monolithic structures of frame multi-story buildings. In contrast to existing methods, which do not allow the comparison of formwork systems, it is proposed to determine the duration of installation and dismantling of formwork using the method of integer rationing, providing for the duration of the steps to establish and fix the components of the formwork to be set in whole numbers depending on the number of movements of the formwork elements and the degree of responsibility for accuracy and reliability of connections. A new approach to determining the duration by the integer method solves the problem of choosing formwork systems.

Published
2020-10-30
How to Cite
ТОНКАЧЕЄВ, Г. М.; ТОНКАЧЕЄВ, В. Г.. DETERMINATION OF THE DURATION OF THE INSTALLATION AND DISMANTLING OF FORMWORK BY INTEGER VALUATION. Building production, [S.l.], v. 1, n. 67, p. 31-36, oct. 2020. ISSN 2524-2555. Available at: <https://ndibv-building.com.ua/index.php/Building/article/view/190>. Date accessed: 23 dec. 2024. doi: https://doi.org/10.36750/2524-2555.67.31-36.